Timeline: F.A. Day Middle School Construction

School is hoping renovations will be complete by Sept. 2012.

As the School Committee at three elementary schools, it's also keeping tabs on progress of Middle School.

At Monday night's special School Committee meeting, Deputy Superintendent/Chief Administrative Officer Sandy Guryan and Building Commissioner Stephanie Gilman informed the committee that the city is on track to choosing a firm for construction designs. 

After nine firms submitted bids, Gilman said four were selected for interviews, which were held Tuesday. Three finalists will be submitted to the mayor, who will award the final bid. 

Find out what's happening in Newtonwith free, real-time updates from Patch.

Once on board, Guryan said the designer will look at presented to the committee, complete construction drawing and costing. At that point, the department will be able to come back to the committee with a better idea of options and pricing for the Day construction.

By September of this year, Guryan said the department should have a more complete update as to what the Day project is actually going to look like, at which point the project will start the process of going out to bid.

Find out what's happening in Newtonwith free, real-time updates from Patch.

Ideally, the committee is looking to have the work done by September 2012 but the current timeline places project completion in January 2013. Guryan said the department is currently working with F.A. Day administration to figure out a contingency plan if the work was not finished by September 2012. 

Here is a current timeline of the F.A. Day construction:

Design funds request/approval Completed Architect request for quotation (RFQ) responses due April 28, 2011 Designer selection meeting May 2, 2011 Design Selection Committee meeting interviews shortlisted firms May 17, 2011 Contract with selected firm May 27, 2011 School Committee update June 13, 2011 Schematic design June 22, 2011 School Committee vote June 27, 2011 Schematic design review by Design Review Committee

July 12, 2011

Docket the project with the Board of Aldermen (two week public hearing notice) July 13, 2011 Site plan approval hearing/Public Facilities Subcommittee approval July 27, 2011 Finance Committee approval July 27, 2011 Full Board of Aldermen approval Aug. 8, 2011 Design development Aug. 16, 2011 Design development review by Design Review Committee Aug. 23, 2011 Construction documents Aug.-Oct. 2011 School Committee update Sept. 12, 2011 Construction documents review by Design Review Committee Oct. 27, 2011 Advertise central register Nov. 15, 2011 Specifications/plans available Nov. 28, 2011 Pre-bid conference Dec. 1, 2011 Filed sub bids due Dec. 12, 2011 General bids due Dec. 20, 2011 Contract awarded Jan. 6, 2012 Construction period March - Aug. 2012 F&E installation and occupancy Phased, starting Jan. 2013

 

Due to increased enrollment, the School Committee late last year to expand the middle school. 

However, the committee learned earlier this year the district , which requires buildings to install sprinkler systems throughout the property during a renovation. With only $5 million bonded by the city to cover the projects, the committee has had to go back and look at new options for both the middle school and elementary schools. 

The committee will meet again Mon., May 23 at 7:30 p.m. and is expected to take a vote on the modular classroom recommendations for the elementary schools.